Project Status and Timeline Update
December 2023
Front-End Community Building Steel and Envelope scheduled to be completed
Which includes a community room, lobby, atrium, canteen, office, pool changing rooms, public washrooms, etc.
December 2023 → September 2024
The Interior Fit-Up of the Entire Building is scheduled to take place.
This includes all plumbing, electrical, heating, and ventilation for the entire building. Plus, all the mechanical requirements for this state-of-the-art facility. In addition, this stage includes the completion of an NHL-sized ice surface, a warm room, spectator seating, boards/glass system, players' benches, 6 dressing rooms, 2 referee rooms, a walking track, a large multi-purpose room, kitchen/canteen, and elevator.